DATE: May 16, 2018
TO: Franklin Municipal Planning Commission
FROM: Josh King, Principal Planner
Amy Diaz-Barriga, Current Planning Supervisor
Emily Hunter, Director of Planning and Sustainability
Subject
title
McEwen Place Town Center PUD Subdivision, Development Plan, Revision 4, Section 3, (Block A), Constructing A 150 Room Hotel And 96,900 Square Feet Of Commercial Space On 4.88 Acres, Located At The Intersection Of Rush Street And W. McEwen Drive.
body
Project Information
COF Project Number: 6677
Applicant: Jack Parker, Catalyst Design
Owner: Chartwell Hospitality
Background/Staff Comments
McEwen Town Center PUD was last revised in 2016 for Blocks B and C based on the previous Concept Plan (2006). This Development Plan revision contains the proposed hotel use (approved under the entitlements) and 96,900 square feet of commercial and retail space. This development plan revision is consistent with Envision Franklin and the intent of the Concept Plan.
Project Considerations
Project Considerations are not conditions of this approval, but are intended to highlight issues that should be considered in the overall site design or may be required when more detailed plans are submitted for review. These items are not meant to be exhaustive and all City requirements and ordinances must be met with each plan submittal.
This block will be developed in two or more phases by Boyle Nashville and Chartwell Group. Structured parking will need to be shown at the appropriate site plan.
Recommendation
recommendation
Approval, with conditions.
end
See attached pages for a list of staff recommended conditions of approval.
PROCEDURAL REQUIREMENTS:
1. If the plan receives BOMA approval, the applicant shall upload the corrected plan to the online plan review website (https://franklin.contractorsplanroom.com/secure/). All revisions to the approved plans shall be "clouded." With the resubmittal, each condition of approval/open issue in t...
Click here for full text