DATE: November 12, 2019
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering
Jimmy Wiseman, Assistant Director of Engineering
SUBJECT:
title
COF Contract No. 2018-0281 Termination of Drainage Easement
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Contract 2018-0281
Background
The Milcrofton Utility District requires an exclusive easement along the existing right-of-way of Carothers Parkway adjacent to the Lockwood Glen POD Subdivision. A portion of the existing drainage easement must be abandoned to accommodate the water main. Drainage features were installed in a manner that does not impact Milcrofton’s water main.
Financial Impact
There is no financial impact to the City of Franklin.
Recommendation
rec
This PSA was executed per the authority granted to the City Administrator by the BOMA via Resolution 2012-05.