File #: 17-0883    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 10/2/2017 In control: Board of Mayor & Aldermen
On agenda: 10/10/2017 Final action: 10/10/2017
Title: Consideration of Resolution 2017-75, "A Resolution Awarding the Construction Contract (COF Contract No. 2017-0198) for the Goose Creek Inn Sanitary Sewer Project to Civil Constructors, Inc. in the Amount of $580,387.60 (9/28/17 CIC 4-0) body Purpose The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution No. 2017-75. Background The Goose Creek Inn Wastewater Treatment Plant (WWTP) (NPDES Permit TN0060216) is a small treatment facility that provides wastewater treatment for the Goose Creek Inn, B&G Rentals (property owner K&T Associates, LLC) and Mapco Family Centers, Inc. (currently inactive sanitary sewer service). The plant has been in operation since the 1960s and has since deteriorated, no longer capable of providing adequate treatment for discharge into Five Mile Creek (mile 2.2). The Tennessee Department of Environment and Conservation (TDEC) performed a Compliance Evaluation Inspection (CEI) in Septem...
Sponsors: Paul Holzen, Jonathan Marston
Attachments: 1. 17-0883 Res 2017-75 Goose Creek Inn Sanitary Sewer Project.Law Approved.pdf, 2. Goose Creek Inn Bid Tabs.pdf

DATE: September 22, 2017

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul P. Holzen, Director of Engineering/City Engineer
Jonathan Marston, Assistant Director of Engineering

SUBJECT:title
Consideration of Resolution 2017-75, "A Resolution Awarding the Construction Contract (COF Contract No. 2017-0198) for the Goose Creek Inn Sanitary Sewer Project to Civil Constructors, Inc. in the Amount of $580,387.60 (9/28/17 CIC 4-0)
body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution No. 2017-75.

Background
The Goose Creek Inn Wastewater Treatment Plant (WWTP) (NPDES Permit TN0060216) is a small treatment facility that provides wastewater treatment for the Goose Creek Inn, B&G Rentals (property owner K&T Associates, LLC) and Mapco Family Centers, Inc. (currently inactive sanitary sewer service). The plant has been in operation since the 1960s and has since deteriorated, no longer capable of providing adequate treatment for discharge into Five Mile Creek (mile 2.2).

The Tennessee Department of Environment and Conservation (TDEC) performed a Compliance Evaluation Inspection (CEI) in September 2011 and in December 2015. On September 23, 2016, Commissioner Martineau issued a Commissioners Order and Assessment (Order) to Mr. Robert Moore Jr., owner of the Goose Creek Inn and treatment facility. In short, the Order requires an aggressive schedule to connect to the City of Franklin's wastewater collection system and to abandon the Goose Creek Inn WWTP.

On August 29, 2017, sealed bids were received by the City of Franklin Engineering Department, 109 3rd Avenue South, Franklin, Tennessee 37064 and were publicly opened and read aloud for the Goose Creek Inn Sanitary Sewer Project (COF Contract No. 2017-0198). After careful review and tabulation of all submitted bids, City staff recommends awarding the construction contract to Civil Constructions,...