File #: 17-0002    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 12/15/2016 In control: Board of Mayor & Aldermen
On agenda: 1/10/2017 Final action: 1/10/2017
Title: Consideration of Change Order No. 3 (Final Change Order) to the Construction Contract for the Hillsboro Road Improvements Project Phase 1, SR96W to Independence Square (COF Contract No. 2012-0110, Resolution 2012-67) (12/15/2016 CIC 4-0)
Sponsors: Eric Stuckey, Paul Holzen, Jonathan Marston, William Banks
Attachments: 1. COF2012-0110_Hillsboro_Rd_Improvements-CO#3_Exh_A

DATE: December 13, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer

SUBJECT:
Consideration of Change Order No. 3 (Final Change Order) to the Construction Contract for the Hillsboro Road Improvements Project Phase 1, SR96W to Independence Square (COF Contract No. 2012-0110, Resolution 2012-67) (12/15/2016 CIC 4-0)
body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 3 to the Construction Contract with Civil Constructors, Inc. for the Hillsboro Road Improvements Project Phase 1, SR96W to Independence Square (COF Contract No. 2012-0110, Resolution 2012-67).

Background
The construction contract for the Hillsboro Road Improvements Project Phase 1, SR-96W to Independence Square, was awarded by the BOMA to Civil Constructors, Inc. on December 11, 2012, for $12,124,758.73. The construction Notice to Proceed stated that the authorized 455 consecutive calendar work days began on February 11, 2013 and ended on May 12, 2014. Change Order No. 1 was approved on July 23, 2013, which included material line item increases. Change Order No. 2 was approved on January 14, 2014 and included a time extension and additional traffic control compensation. That time extension changed the date of completion of all work from May 12, 2014 to July 7, 2014.

This Change Order No. 3 is the final change order and project closeout. Reasons for Change Order No. 3 include:

1. Time extension due to the following issues: Excavation for Wall #2 could not be completed until the AT&T VRAD was relocated. The meeting minutes show Civil needing to start excavation at Wall #2 the 1st week of December 2013, but this excavation could not be completed due to the VRAD relocation until March 13th, 2014. Not only did the relocation of the VRAD delay com...

Click here for full text