File #: 16-0908    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/14/2016 In control: Work Session
On agenda: 11/8/2016 Final action: 11/8/2016
Title: *Consideration of Resolution 2016-72, Awarding the Construction Contract (COF Contract No. 2015-0070) for the Goose Creek Sanitary Sewer Extension Project, From West of I-65 to the East Side of I-65, to Dynamic Construction, LLC in the Amount of $1,717,620.40. (Deferred from 10-27-16 Capital Investment Committee)
Sponsors: Paul Holzen, Mark Hilty, Patricia McNeese
Attachments: 1. AWARD REC LTR 092616, 2. Resolution 2016-72 to award bid Goose Creek Sewer Project.Law Approved

DATE: October 27, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, P.E., Director of Engineering
Mark Hilty, P.E., Director of Water Management
Patricia McNeese, P.E., Utilities Engineer II

SUBJECT:
title
*Consideration of Resolution 2016-72, Awarding the Construction Contract (COF Contract No. 2015-0070) for the Goose Creek Sanitary Sewer Extension Project, From West of I-65 to the East Side of I-65, to Dynamic Construction, LLC in the Amount of $1,717,620.40. (Deferred from 10-27-16 Capital Investment Committee)
body

Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2016-72, which awards the Construction Contract (COF Contract No. 2015-0070) for the Goose Creek Sanitary Sewer Extension Project, from west of I-65 to the east side of I-65, to Dynamic Construction, LLC in the amount of $1,717,620.40.

Background
On September 23, 2016, the City of Franklin Engineering Department received and opened bids for the Goose Creek Sanitary Sewer Extension Project, from west of I-65 to the east side of I-65. The low bidder was Dynamic Construction, LLC, and they have provided adequate experience for a project of this magnitude. A recommendation letter from Hethcoat and Davis, including a bid tabulation summary, has been included for review.

Financial Impact
Below is the financial impact, based on the Amendment No. 1 to the Agreement from Goose Creek Sanitary Sewer Extension from West of I-65 to East of I-65 (COF Contract No. 2014-0051) approved by the BOMA on January 13th, 2015:

$1,717,620.40 Total Construction/Bid Cost
$ 510,121.60 HPT TA Properties Anticipated Reimbursement
$1,207,498.80 COF Anticipated Cost (Sewer Operating Funds)

The City is also pursuing a reimbursement in the amount of $152,120.98 for the design engineering, permitting, construction management, inspection and easement acquisition from ...

Click here for full text