File #: 16-0903    Version: 1 Name: Contract amendment 2 to 2013-0182
Type: Contract/Agreement Status: Passed
File created: 10/14/2016 In control: Board of Mayor & Aldermen
On agenda: 11/22/2016 Final action: 11/22/2016
Title: Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. for the Figuers Drive Area Drainage Improvements Project at a Cost Increase of $29,500.00 (Deferred from 10-27-16 Capital Investment Committee; 11/08/16 WS)
Sponsors: Paul Holzen, William Banks
Attachments: 1. COF_2013-0182_Figuers_Drive_Drainage_PSA-AMEND_2 with scope.Law Approved

DATE: October 27, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul P. Holzen, Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. for the Figuers Drive Area Drainage Improvements Project at a Cost Increase of $29,500.00 (Deferred from 10-27-16 Capital Investment Committee; 11/08/16 WS)
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the Amendment No. 2 proposal from Neel-Schaffer, Inc. to modify their existing Professional Services Agreement (PSA) for the Figuers Drive Area Drainage Improvements Project

Background
On November 26, 2013, the Board of Mayor and Aldermen approved a PSA (COF Contract No. 2013-0182) with Neel-Schaffer for the Preliminary Engineering of the Figuers Drive Area Drainage Improvements Project. This PSA allowed Neel-Schaffer to provide the City with a detailed preliminary plan as to what improvements can be made to help the Figuers Drive Area residents with their ongoing flooding issues.

Amendment No. 1 was approved by BOMA on August 11, 2015. It included fees for the following:
1. Final design of the Figuers Drive East Option 2, for the flooding area near Franklin Elementary School. This Option 2 contains the Option 1 recommended drainage improvements as well as grassed channel improvements along the existing Quarry Branch channel, replacement of cross drains, installation of a diversion structure upstream of Figuers Drive, installation of a storm sewer system along Figuers Drive to Perkins Drive, and construction of a grassed diversion channel from Perkins Drive to Alicia Drive. It is anticipated that the Figuers Drive East Option 2 will provide an approximate 100-year level of protection for the affected homes.
2. Final design of the Figuers Drive West area ...

Click here for full text