File #: 16-0903    Version: 1 Name: Contract amendment 2 to 2013-0182
Type: Contract/Agreement Status: Passed
File created: 10/14/2016 In control: Board of Mayor & Aldermen
On agenda: 11/22/2016 Final action: 11/22/2016
Title: Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. for the Figuers Drive Area Drainage Improvements Project at a Cost Increase of $29,500.00 (Deferred from 10-27-16 Capital Investment Committee; 11/08/16 WS)
Sponsors: Paul Holzen, William Banks
Attachments: 1. COF_2013-0182_Figuers_Drive_Drainage_PSA-AMEND_2 with scope.Law Approved

 

DATE:                                                               October 27, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul P. Holzen, Director of Engineering

                                          William Banks, Staff Engineer

                     

SUBJECT:                                          

title

Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. for the Figuers Drive Area Drainage Improvements Project at a Cost Increase of $29,500.00  (Deferred from 10-27-16 Capital Investment Committee;  11/08/16 WS)   

body

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the Amendment No. 2 proposal from Neel-Schaffer, Inc. to modify their existing Professional Services Agreement (PSA) for the Figuers Drive Area Drainage Improvements Project

 

Background

On November 26, 2013, the Board of Mayor and Aldermen approved a PSA (COF Contract No. 2013-0182) with Neel-Schaffer for the Preliminary Engineering of the Figuers Drive Area Drainage Improvements Project.  This PSA allowed Neel-Schaffer to provide the City with a detailed preliminary plan as to what improvements can be made to help the Figuers Drive Area residents with their ongoing flooding issues. 

 

Amendment No. 1 was approved by BOMA on August 11, 2015.  It included fees for the following:

1.                     Final design of the Figuers Drive East Option 2, for the flooding area near Franklin Elementary School.  This Option 2 contains the Option 1 recommended drainage improvements as well as grassed channel improvements along the existing Quarry Branch channel, replacement of cross drains, installation of a diversion structure upstream of Figuers Drive, installation of a storm sewer system along Figuers Drive to Perkins Drive, and construction of a grassed diversion channel from Perkins Drive to Alicia Drive.  It is anticipated that the Figuers Drive East Option 2 will provide an approximate 100-year level of protection for the affected homes.

2.                     Final design of the Figuers Drive West area near 417/419 Figuers Drive and 417/419 Perkins Drive.  This option generally consists of removing an existing cross drain downstream of Perkins Drive and upgrading culverts at Perkins and Figuers Drive.  Local site grading will be necessary to further improve the localized flooding and drainage issues.  It is anticipated this will provide an approximate 50-year level of protection for the affected homes. 

 

This Amendment No. 2 includes fees to resolve the existing water and sewer line utility conflicts with the newly proposed storm water drainage designed during Amendment #1, specifically:

1.                     Water line improvements consisting of replacing approximately 1,450 linear feet of existing 6-inch transite water line on Figuers Drive and Alicia Drive with a new water line of a material and size as selected by the City.  The proposed maximum hourly fee for the Scope of Work contained in Exhibit A, will be $15,500.00.

2.                     Sewer improvements consisting of intercepting the existing 8-inch gravity sewer line from the Franklin Elementary School on Figuers Drive and installing approximately 500 linear feet of new 8-inch gravity sewer line and manholes along Figuers Drive to a new manhole on the 10-inch gravity sewer line on Alicia Drive.  The proposed maximum hourly fee for the Scope of Work contained in Exhibit A, will be $14,000.00.

 

Financial Impact

The original PSA (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. for preliminary engineering was at a not-to-exceed cost of $82,000.00.  Amendment No. 1 to the PSA with Neel-Schaffer, Inc. for final design was in the amount of $125,200.00. This created a new, not-to-exceed total contract cost of $207,200.00. 

 

This Amendment No. 2 to the PSA with Neel-Schaffer, Inc. for utility relocation design is in the amount of $29,500.00.  This creates a new, not-to-exceed total contract cost of $236,700.00. 

 

All costs will be paid for out of the FY2016-2017 Stormwater Fund under Capital, $X.

 

Recommendation

rec

Staff recommends approval of Amendment No. 2 to the PSA (COF Contract No. 2013-0182) with Neel-Schaffer, Inc. at a cost increase of $29,500.00