File #: 14-679    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 11/19/2014 In control: Board of Mayor & Aldermen
On agenda: 1/13/2015 Final action: 1/13/2015
Title: Consideration of Change Order No. 5 (Final Change Order) to the Construction Contract for the 3rd Avenue North Extension Project (Bicentennial Park Phase I) (COF Contract No. 2012-0089) for a decrease in the amount of $36,010.99 (12/09/14 WS)
Sponsors: Paul Holzen
Attachments: 1. COF2012-0089 3rd Ave N Ext - CO#5 EXHIBITA 12-10-14
DATE: November 19, 2014

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of Change Order No. 5 (Final Change Order) to the Construction Contract for the 3rd Avenue North Extension Project (Bicentennial Park Phase I) (COF Contract No. 2012-0089) for a decrease in the amount of $36,010.99 (12/09/14 WS)
body

Purpose
The purpose of this memorandum is to recommend approval to the Board of Mayor and Aldermen (BOMA) of Change Order No. 5 (Final Change Order) to the construction contract with SiteSolutions/The Parkes Companies, Inc. for the 3rd Avenue North Extension Project (Bicentennial Park Phase I)(COF Contract No. 2012-0089).

Background
The 3rd Avenue North Extension (Bicentennial Park Phase I) construction contract was awarded by BOMA to The Parkes Companies, Inc. on August 14, 2012, for $4,795,129.72. The anticipated project completion was September 2013. Change Order No. 1 was approved by BOMA on October 23, 2012, for a decrease of $416,362.43. It replaced some existing bid line items with the alternate Redi-Rock Wall bid line items, causing a substantial cost savings. Change Order No. 2 was approved by BOMA on January 8, 2013, which included small changes required to properly complete the project, but no contract price increase. Change Order No. 3, a cost increase of $242,409.68, was approved on February 12, 2013, and included adding limestone caps for the bridge, Redi-Rock bridge headwall and a credit for reducing the size of our water main from 10" to 6". Change Order No. 4 was approved by BOMA on August 8, 2013, included a time extension of 120 days for a total contract time of 485 calendar days (originally 365, plus 120).

This Change Order No. 5 includes both the balancing of final line item quantities (Project Closeout) and a request for additional tim...