File #: 19-1203    Version: 1 Name: procurement award for Holiday Court sewer system improvements
Type: Contract/Agreement Status: Passed
File created: 11/8/2019 In control: Board of Mayor & Aldermen
On agenda: 3/10/2020 Final action: 3/10/2020
Title: Consideration Of Procurement Award To Middle Tennessee Infrastructure, Inc. Of Murfreesboro, Tennessee In The Total Amount Of $554,057.40 For Holiday Court Sewer System Improvements For The Sewer-General Division Of The Water Management Department (Purchasing Office Procurement Solicitation No. 2020-017; City Project No. 2019-016; $500,000 Budgeted In 431-89320-52219 For Fiscal Year 2020; City Contract No. 2019-0310) (WS 2/25/20)
Sponsors: Michelle Hatcher, Brian Goodwin
Attachments: 1. 2020-017 Tabulation of bids 2020.02.19.1119, 2. 2019-0310 C-520 Agreement with all but attachments 2a, 2b and 9c.Law Reviewed, 3. 2020-017 Tabulation of bid line-item pricing 2020.02.06, 4. Master

 

DATE:                                                               February 19, 2020

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric S. Stuckey, City Administrator

                                          Mark Hilty, Assistant City Administrator - Public Works

                                          Kristine Brock, Assistant City Administrator / CFO

                                          Michelle Hatcher, PE, Director, Water Management Department

                                          Brian Goodwin, PE, Assistant Director, Water Management Department

                                          Brian Wilcox, Purchasing Manager

 

SUBJECT:

title

Consideration Of Procurement Award To Middle Tennessee Infrastructure, Inc. Of Murfreesboro, Tennessee In The Total Amount Of $554,057.40 For Holiday Court Sewer System Improvements For The Sewer-General Division Of The Water Management Department (Purchasing Office Procurement Solicitation No. 2020-017; City Project No. 2019-016; $500,000 Budgeted In 431-89320-52219 For Fiscal Year 2020; City Contract No. 2019-0310) (WS 2/25/20) 

body

 

Purpose

The purpose of this procurement is to purchase Holiday Court sewer system improvements for the Wastewater Collection Division of the Water Management Department. The primary purpose of the improvements is to rehabilitate the Holiday Court sanitary sewer pump or lift station which staff estimates was constructed in the early 1980s and has outlived its expected service life.

 

Background

The City published on January 2, 2020 a Notice to Bidders in the Williamson Herald for Holiday Court sewer system improvements. In addition, bid documents were sent on or about the same date directly to seven (7) potential bidders known or thought to be interested in this solicitation. Bids from three (3) contractors were publicly opened at the bid opening held on February 4, 2020. Both a tabulation of the bids received for this solicitation and a tabulation of bid line-item pricing are attached.

 

Financial Impact

The responsible bidder that submitted the lowest priced responsive bid is Middle Tennessee Infrastructure, Inc. of Murfreesboro, Tennessee, in the total amount of $554,057.40 for the specified project. This bid was identified because it is the lowest bid that meets or exceeds the City’s intention as expressed and implied by the City’s specifications as well as the instructions, terms and conditions pertaining to this procurement solicitation. The engineer’s October 9, 2017 opinion of construction cost is, in total, $564,000. The Water Management Department Sewer-General Division budget for fiscal year 2020 allocates $500,000 out of the Sewer Fund for the Holiday Court lift station rehabilitation. The Middle Tennessee Infrastructure, Inc. bid amount is $54,057.40 (about 10.8%) over budget.

 

Options

In accordance with the bid documents, the City reserves the right to reject any and all bids.

 

Recommendation

rec

Staff recommends that the City accept, contingent upon Law Department and City Administrator approval of City Contract No. 2019-0310, the apparent lowest best bid, from Middle Tennessee Infrastructure, Inc. of Murfreesboro, Tennessee, in the total amount of $554,057.40 for the specified project, and award this procurement to this bidder. The City’s Purchasing Manager believes the prepared solicitation documents as distributed allowed for competition among multiple service providers, and that the staff recommendation appears to be made in a fair and impartial manner based upon the proposals received. Pursuant to authority previously granted by the Board of Mayor and Aldermen, Contract No. 2019-0310 has been prepared for execution by the City Administrator and is attached pending approval by the Board of Mayor and Aldermen of the staff recommendation to accept the bid from and award the procurement to Middle Tennessee Infrastructure, Inc.