File #: 20-0239    Version: 1 Name:
Type: Presentation Status: Agenda Ready
File created: 2/24/2020 In control: Capital Investment Committee
On agenda: 3/26/2020 Final action:
Title: Discussion Concerning Morningside Detention Pond. (CIC 2/27/20)
Attachments: 1. Morningside Pond exhibit.pdf, 2. Notice of Inspection (Morningside, Sec 8, Lot 19).pdf

DATE: February 24, 2020

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering

SUBJECT:
title
Discussion Concerning Morningside Detention Pond. (CIC 2/27/20)
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning an existing detention pond located in the Morningside Development.

Background
This item was added to the agenda at the request of Aldermen McLendon. Below is a summary of the background and history.

* February 3, 2003 - City staff approved the Brentwood Pointe Phase II - Lot 8 Grading and Drainage Plan. This plan included a detention pond and outlet structure located on the proposed Morningside Development. A note on the grading plan states the following: "Both Morningside and Brentwood Pointe are under legal control of Haury & Smith. Final Public Drainage Easement will be recorded at the time of recording Morningside. Maintenance of the Facility shall be the joint responsibility of the two entities referenced above."

* March 5, 2004 - City staff approved Morningside Section 8, Lot 19 Grading and Drainage Plan. This plan showed the approved Brentwood Pointe Phase II - Lot 8 Drainage Pond.

* March 17, 2004 - Haury & Smith Contractors, Inc. signed and recorded an inspection and maintenance Agreement of Private Stormwater Management Facilities for Morningside, Section 8, Lot19 and had the document recorded at the Williamson County Registers Office.

* May 20, 2004 - Franklin Municipal Planning Commission approved the Final Plat of Morningside PUD Subdivision.

* March 24, 2005 - Franklin Municipal Planning Commission approved the Section Eight - Final Plat of Brentwood Point III PUD Villages of Morningside - Lot 19.

The stormwater maintenance within both developments are designated as "private" on both plats. On December 2, 2019, City staff completed an inspection of the facility an...