File #: 20-0136    Version: 1 Name:
Type: Contract/Agreement Status: Consent Agenda
File created: 1/27/2020 In control: Board of Mayor & Aldermen
On agenda: 3/24/2020 Final action:
Title: Consideration Of A Change Order No. 3 To COF Contract No. 2017-0264 With Kiewit Infrastructure South Co, For The Water Reclamation Facility Modifications & Expansion Project. (CIC 2/27/20, 3-0)
Sponsors: Michelle Hatcher
Attachments: 1. 20200224_CHANGE_Kiewit Change Order No. 3 - LAW APPROVED_V2.pdf

 

DATE:                                                               January 27, 2020

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Michelle Hatcher, Director, Water Management Department

                     

                                          

SUBJECT:                                          

title

Consideration Of A Change Order No. 3 To COF Contract No. 2017-0264 With Kiewit Infrastructure South Co, For The Water Reclamation Facility Modifications & Expansion Project. (CIC 2/27/20, 3-0) 

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the Change Order No. 3 to the Water Reclamation Facility Upgrades & Expansion Project.

 

Background

The Board of Mayor and Alderman passed a resolution to award a contract on July 10, 2018 for the Water Reclamation Facility Modifications & Expansion Project to Kiewit Infrastructure South Co. (Kiewit).  The amount of the contract entered in to by the City and Kiewit was for $132,890,000.00 (which included an Owner’s contingency amount of $4,000,000.00).  The project specifications have a substantial completion date of February 20, 2022 and a final completion date of May 26, 2022.

 

During the course of the project to date, the need for various changes to Kiewit’s scope became apparent to include work not captured in the original contract, changes due to alternative items of equipment, or to realize savings to the City.  Those changes are memorialized in Construction Change Authorizations (CCAs), Request For Proposals (RFPs), and Change Proposals (CPs) issued by CDM Smith and the City, and formalized in this Change Order No. 3.

 

The attached Change Order No. 3 reflects these changes that have been encountered to date and are summarized below:

                     CCA No. 9: remote HVAC indication

                     CCA 12: Equalization tank finished grade revisions

                     CCA 20: waste gas burner flame CP revisions

                     CCA 22: delete combustible gas monitor

                     CCA 26: revised headworks hatch dimensions

                     RFP 4: jet mixing system revisions

                     CP 3: fabricated softened water tanks

                     CP 9: auxiliary power & controls to combined heat & power generator

                     CP 10: CROM warranty revisions & credits

 

Financial Impact

This Change Order No. 2 provides for a net change order decrease of $87,064.00 to the contract terms.

 

Recommendation

rec

Staff recommends approval of this Change Order No. 3 to the contract with Kiewit Infrastructure South.