File #: 20-0145    Version: 2 Name:
Type: Presentation Status: Agenda Ready
File created: 1/28/2020 In control: Work Session
On agenda: 2/11/2020 Final action:
Title: Discussion And Consideration On The City Participating In The Road Impact Fee Development Agreement For The Proposed Southbrooke Development By Contributing Additional Funding For The Purpose Of The Southbrooke Developer Fully Improving The Goose Creek Bypass/Lewisburg Pike Intersection.
Sponsors: Vernon Gerth, Paul Holzen
Attachments: 1. COF 2019-0221 Exhibit A (Intersection Improvements Only).pdf

 

DATE:                                                               February 11, 2020

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Vernon Gerth, Assistant City Administrator - Community/Economic Development

                                          Jimmy Wiseman, Assistant Director of Engineering

                                          Michael Walters Young, Budget and Strategic Innovation Manager

                                          

SUBJECT:                                          

title

Discussion And Consideration On The City Participating In The Road Impact Fee Development Agreement For The Proposed Southbrooke Development By Contributing Additional Funding For The Purpose Of The Southbrooke Developer Fully Improving The Goose Creek Bypass/Lewisburg Pike Intersection. 

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Contributing Additional Funding For The Purpose Of The Southbrooke Developer Fully Improving The Goose Creek Bypass/Lewisburg Pike Intersection.

 

Background

The Southbrooke Development is proposing 205 residential units south of Goose Creek Bypass on Lewisburg Pike.  The traffic impact analysis currently shows a level of service F without any improvements to the intersection.  The additional traffic includes the development and background growth.  The full buildout of the north, south and eastern legs of the intersection is recommended.  The arterial impact fees generated by the Southbrooke PUD will total $922,202.  The estimated cost of the recommended improvements is $2,974,930.

 

Financial Impact

$922,202 will be paid by the developer in arterial impact fees.  An additional $2,052,728 is needed for the arterial improvements.  The City’s Road Impact Fund has a considerable fund balance of $16,589,763 as of June 30, 2019 and nearly 75% of that balance is attributable to arterial impact fees. In addition, year-to-date collections in arterial impact fees are nearly $4.7 million through the first six months of the fiscal year compared to a forecast estimate of $5.8 million.

 

It should be noted, however, that there are already sizeable reservations against these funds including over in $14.4 million arterial impact fees planned for use in funding approved FY 2019-2028 CIP Projects, as well as ongoing debt service against this fund ranging around $3 million annually.

 

Overall, staff believes there is sufficient fund balance to afford this expense at this time weighing existing cash in hand, performance to date and the fact that the $14.4 million in arterial impact fees planned for approved CIP projects is not needed all in one year, rather spread out during the 10 year duration of the plan.

 

Finally, and most importantly, although the Road Impact fund has a sufficient fund balance to cover these additional improvements, it is the BOMA that should decide to participate in this intersection improvement of this magnitude given that it is not a project which has been approved as part of the ten-year Capital Investment Program.

 

Recommendation

rec

Staff recommends allocating funding needed to support improvements at the Lewisburg Pike-Goose Creek intersection.