File #: 19-1117    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 10/16/2019 In control: Capital Investment Committee
On agenda: 10/24/2019 Final action:
Title: Consideration of a DRAFT Professional Services Agreement (COF Contract No. 2019-0317) with Alfred Benesch & Company for the Final Design of the Multi-Use Trail & Bridge at The Park at Harlinsdale Farm in an Amount Not-to-Exceed $398,268.00
Sponsors: Engineering
Attachments: 1. Contract_2019-0317_PSA_Benesch_FinalDesign_HarlinsdaleTrailBridge_.pdf, 2. Contract_2019-0317_Scope_Benesch_FinalDesign_HarlinsdaleTrailBridge_.docx.pdf

DATE: October 16, 2019

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering

SUBJECT:
title
Consideration of a DRAFT Professional Services Agreement (COF Contract No. 2019-0317) with Alfred Benesch & Company for the Final Design of the Multi-Use Trail & Bridge at The Park at Harlinsdale Farm in an Amount Not-to-Exceed $398,268.00
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a Professional Services Agreement (PSA) with Alfred Benesch & Company (Benesch).

Background
In 2018, the City of Franklin was selected to receive $2,000,000 in federal funds through the 2017 Transportation Alternatives Program (TAP) grant cycle to help fund the construction of a multi-use trail and pedestrian bridge at The Park at Harlinsdale Farm. On June 11, 2019, the BOMA approved a PSA (COF Contract No. 2019-0167) with Benesch in an amount not-to-exceed $29,176 to perform the initial due diligence and preliminary coordination for this project. This work is now complete, and the project is ready for final design.

This PSA (COF Contract No. 2019-0317) includes the full and final design for this project, including: (1) survey, (2) hydraulic modeling & analysis, (3) completion of the required environmental clearance phase, (4) design of the multi-use trail & bridge, and (5) the production and submittal of all required permits.

Financial Impact
The total cost of this PSA is $398,268.00. Funding for this project is entirely the responsibility of the City and has been programmed to be expensed to the Hotel/Motel Tax fund. The General Ledger (GL) code to be used for project expenses associated with this PSA is anticipated to be 150-89310-44700.

Recommendation
rec
Staff recommends approval of the PSA (COF Contract No. 2019-0317) with Alfred Benesch & Company in the amount...