File #: 19-0693    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 6/25/2019 In control: Work Session
On agenda: 7/9/2019 Final action: 7/9/2019
Title: *Consideration of Change Order No. 1 (Final Change Order) to the Contract (COF Contract No. 2017-0186) with Adams Contracting, LLC for the Construction of the Carnton Lane Culvert Replacement Project for a Cost Increase of $81,734.46 and a Time Extension of 80 Days
Sponsors: Engineering
Attachments: 1. C2017-0186_CO1_CarntonLaneCulvert.pdf

DATE: June 25, 2019

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering
David Hodnett, Staff Engineer 2

SUBJECT:
title
*Consideration of Change Order No. 1 (Final Change Order) to the Contract (COF Contract No. 2017-0186) with Adams Contracting, LLC for the Construction of the Carnton Lane Culvert Replacement Project for a Cost Increase of $81,734.46 and a Time Extension of 80 Days
body

Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 to the contract with Adams Contracting, LLC for the construction of the Carnton Lane Culvert Replacement Project.

Background
On July 10, 2018, the BOMA approved Resolution 2018-57 to award COF Contract No. 2017-0186 for the construction of a replacement box bridge over Saw Mill Creek on Carnton Lane. This replacement bridge was necessary to replace the existing, deteriorated corrugated metal pipe. The original contract price was $256,225.10 with a total contract time of 90 calendar days. Resolution 2018-57 also established a project contingency of $75,000.00 to expedite the handling of any changes due to unforeseen conditions.

The effective date of the Notice to Proceed was October 8, 2018. With a contract length of 90 days, the date of completion was established as January 6, 2019. Well into construction, a water line, which was not previously located, was discovered to be in direct conflict with the continued construction of the project. The time needed to design a relocation plan and to obtain proper permitting caused significant delay to the project schedule. The delay for the water line relocation also delayed the final paving until Spring 2019.

Change Order No. 1 is the final, close-out change order for this project. The cost overrun of $81,734.46 includes: $66,380.00 for the wat...

Click here for full text