File #: 19-0036    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 1/8/2019 In control: Board of Mayor & Aldermen
On agenda: 2/12/2019 Final action: 2/12/2019
Title: Consideration of Final Reconciling Change Order to Construction Contract (COF Contract No. 2017-0198) with Civil Constructors, LLC for the Goose Creek Inn Sanitary Sewer Extension Project for a Decrease in the Amount of $89,195.80 and a Time Extension Through August 24, 2018. (01/24/19 CIC 4-0)
Sponsors: Michelle Hatcher, Patricia McNeese
Attachments: 1. 2017-0198 Final Reconciling Change Order

DATE: January 8, 2019

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Mark Hilty, Assistant City Administrator for Public Works
Michelle Hatcher, Director of Water Management
Patricia McNeese, Utilities Engineer II


SUBJECT:
title
Consideration of Final Reconciling Change Order to Construction Contract (COF Contract No. 2017-0198) with Civil Constructors, LLC for the Goose Creek Inn Sanitary Sewer Extension Project for a Decrease in the Amount of $89,195.80 and a Time Extension Through August 24, 2018. (01/24/19 CIC 4-0)
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Final Reconciling Change Order to Construction Contract (COF Contract No. 2017-0198) with Civil Constructors, LLC for the Goose Creek Inn Sanitary Sewer Extension Project.

Background
The Goose Creek Sanitary Sewer Extension Project construction project was awarded by the BOMA to Civil Constructors, LLC on October 10, 2017, in the amount of $580,387.60. The construction contract time started on February 5, 2018 with a date of completion of May 6, 2018 (90 calendar days). In October 2018, the BOMA approved Change Order No. 1, which increased the time of completion to June 3, 2018 (28 additional calendar days).

The proposed Final Reconciling Change Order details include the following:

1. Final reconciliation and balancing of all miscellaneous contract line items.
2. Add line items Silt Fence with Wire Backing and Filtrexx Siltsoxx as approved by the Construction Change Authorization No. 1, which was paid for out of the contingency line item.
3. Add the line item Additional Milling and Cleaning for Roadway Crossing.
4. Adjust the cost of the asphalt per ton based on what was shown on the plans and what was actually installed.
5. Add line item for liquidated damages in the amount of $41,000.00 (82 calendar days at $500 per day)
6. Time extension of 82 days to substantial c...