File #: 18-0546    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 5/15/2018 In control: Capital Investment Committee
On agenda: 5/24/2018 Final action:
Title: Consideration of Change Order No. 2 to the Construction Contract (COF Contract No. 2015-0002) with Eutaw Construction Company, Inc. for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway (TDOT PIN 108409.00)
Sponsors: Paul Holzen, Jonathan Marston, William Banks
Attachments: 1. COF2015-0002_Hillsboro_Rd_CO#2_Exhibit_A, 2. COF2015-0002_Hillsboro_Rd_CO#2_Exhibit_A

DATE: May 24, 2018

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of Change Order No. 2 to the Construction Contract (COF Contract No. 2015-0002) with Eutaw Construction Company, Inc. for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway (TDOT PIN 108409.00)
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 2 to the construction contract (COF Contract No. 2015-0002, TDOT PIN 108409.00) with Eutaw Construction Company, Inc. for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway.

Background
The Hillsboro Road Improvements Project Phase 2 construction contract was awarded by the BOMA to Eutaw Construction Company, Inc. on March 8, 2016, in the amount of $11,995,005.13. The construction contract time started on April 18, 2016, with a contract completion date of June 21, 2017 (430 Calendar Days).

Change Order No. 1 was approved by the BOMA in May 2017. This change order included contract line item additions, line item deletions, and a time extension of 154 calendar days (584 total calendar days). The new completion date was set at November 22, 2017.

The proposed Change Order No. 2 details include the following:

1. Add item number 795-50.10, Additional Work (install DDCV (double detector check valve) with FDC assembly (fire department connection) and vault), Lump Sum to the contract documents. The new plans specified fire service line to Franklin High School did not include this check valve, which is required by the City of Franklin Fire Department.
2. Add item no. 730-12.20, Decorative Traffic Signal Bases, EA., to the contract documents. This item is required for the traffic sign...

Click here for full text