File #: 18-0482    Version: 1 Name:
Type: Report Status: Passed
File created: 5/1/2018 In control: Capital Investment Committee
On agenda: 5/24/2018 Final action:
Title: Discussion Concerning Repairs to the Spencer Creek Road Stone Wall
Sponsors: Mark Hilty, Paul Holzen, Joe York, Amanda Rose
Attachments: 1. Estimate_1479_from_G_and_G_Lawncare_LLC, 2. Cheekwood Exhibit

 

DATE:                                                               May 1, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Vernon Gerth, Assistant City Administrator for Community Development

                                          Mark Hilty, Assistant City Administrator for Public Works

                                          Paul Holzen, Director of Engineering                                          

                                          Joe York, Street Department Director

                                          Amanda Rose, Preservation Planner                     

                                          

SUBJECT:                                          

title

Discussion Concerning Repairs to the Spencer Creek Road Stone Wall

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning repairs needed to the Spencer Creek Road stone wall.

 

Background

The stone wall on Spencer Creek Road adjacent to the Cheekwood development and the Cheekwood Golf Course is deteriorating and has become a safety concern. Motorists on Spencer Creek occasionally must avoid rocks that have fallen from the wall into the roadway. The wall is considered to be historic and all the good stone should be saved and restacked. The city has received quotes to demo the existing wall, store the salvageable stone that can be reused, regrade the area, and rebuild the wall with the stored good stone.

 

Financial Impact

G & G Lawncare LLC has provided an estimate of $48,500.00 for the following work:

                     Excavation of 300 feet of roadway ditch;

                     Debris removal;

                     Installation of a 30-inch tall natural stone retaining wall using existing stone on site, with compacted gravel base footer;

                     The removal of all excess stone;

                     Gravel backfill; and

                     Installation of a 1-4 inch ADS French drain pipe behind the wall.

Funding is not available for the project in the current budget. However, the project could be funded after the first of the fiscal year from one of several general fund budgets. A budget amendment would be required to replenish the funds.  Given the estimated project cost, the project would be required to go through a public bid process to comply with purchasing policies

 

Recommendation

rec

Staff recommends approval to proceed with having this section of the historic stone wall located along Spencer Creek Road re-located and we are seeking direction and feedback from the Board.