File #: 18-0471    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 4/27/2018 In control: Board of Mayor & Aldermen
On agenda: 5/22/2018 Final action: 5/22/2018
Title: Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0160) with Gresham Smith and Partners for Construction Administration, Engineering, and Inspection Services for the Hillsboro Road Improvements Phase 2, Independence Square to Mack Hatcher Parkway, in an Amount Not-to-Exceed $84,000.00. (4/27/2018 CIC 3-0)
Sponsors: Paul Holzen
Attachments: 1. 2014-0160 Amendment 1_Gresham Smith_Hillsboro Rd_PSA_with attachment.Law Approved

 

DATE:                                                               April 26, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineer/Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering

                                          William Banks, Staff Engineer                     

                                          

SUBJECT:                                          

title

Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0160) with Gresham Smith and Partners for Construction Administration, Engineering, and Inspection Services for the Hillsboro Road Improvements Phase 2, Independence Square to Mack Hatcher Parkway, in an Amount Not-to-Exceed $84,000.00. (4/27/2018 CIC 3-0)

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 1 to the Professional Services Agreement (PSA) with Gresham Smith and Partners (GS&P) for construction administration, engineering, and inspection (CEI) services for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway.

 

Background

The Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway, started construction in April of 2016.  Due to the use of state and federal funds, the Tennessee Department of Transportation (TDOT) requires full CEI services on this project.   GS&P was selected by the City to perform day-to-day construction administration, to document inspections, and to assist in coordination between the City and TDOT.  The BOMA approved the original PSA (COF Contract No. 2014-0160) with GS&P on September 9, 2014.

 

The original PSA included funds for a 14-month construction contract and a 1-month close-out period.  Due to utility conflicts and other construction issues, the construction contract was extended by 5 months.  GS&P was able to budget their inspection time and original fees to accommodate the extended 5 months of contract time though November 2017.  Furthermore, GS&P was able to use the fee listed in the original PSA to provide their services through February 2018, without the need for additional funds.  Because the contractor is still not complete (as of April 2018), GS&P has continued to perform in their inspection role on the job site. 

 

Amendment No. 1 allows for additional CEI services, both day-to-day inspection and project closeout documentation, through July 2018.  See the attached Scope of Services (Attachment A), dated April 17, 2018, from GS&P, for detailed information.

 

Financial Impact

The cost of Amendment No. 1 is $84,000.00.  Expenses will continue to be paid from the Capital Project Fund, with the main source of funding being the 2017 General Obligation Bond issue.  Therefore, the General Ledger (GL) code to be utilized for project expenses is 311-89420-43100.  These costs will be reimbursed by TDOT.

 

Recommendation

rec

Staff recommends approval of Amendment No. 1 to the PSA (COF Contract No. 2014-0160) with Gresham Smith and Partners in an amount not-to-exceed $84,000.00.