File #: 18-0455    Version: 1 Name:
Type: Resolution Status: Filed
File created: 4/27/2018 In control: Work Session
On agenda: 6/12/2018 Final action: 6/12/2018
Title: Consideration of Resolution 2018-37, A Resolution To Approve An Alternative Preliminary Design Concept For The 100-Block Battle Avenue Drainage Improvements Project And Authorize Staff To Complete Right-Of-Way Acquisition, Final Design And Construction (04/26/18 CIC recommended Option 2B to BOMA 3-0) (05/08/18 WS to 6/12/18 Work session; 6/12/18 WS referred to 6/26/18 WS).
Sponsors: Paul Holzen
Attachments: 1. BATTLE AVE PRESENTATION 4-2018.pdf, 2. Res 2018-37 Battle Ave Drainage Improvements_with Exhibit A.Law Approved, 3. Stormwater Forecast - FY 2019-2022.pdf
Related files: 18-0340

 

DATE:                                                               April 6, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering

                     

                                          

SUBJECT:

                                          

title

Consideration of Resolution 2018-37, A Resolution To Approve An Alternative Preliminary Design Concept For The 100-Block Battle Avenue Drainage Improvements Project And Authorize Staff To Complete Right-Of-Way Acquisition, Final Design And Construction (04/26/18 CIC recommended Option 2B to BOMA 3-0) (05/08/18 WS to 6/12/18 Work session; 6/12/18 WS referred to 6/26/18 WS).

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the Battle Ave Project.

 

Background

On November 26, 2013, the Board of Mayor and Aldermen approved a Professional Services Agreement (COF Contract 2013-0180) with Neel-Schaffer, Inc. for engineering design services, including additional drainage modeling and preparation of contract plans and specifications, on the 100 Block Battle Avenue Drainage Improvements Project.  

 

On December 9, 2014 Resolution 2014-50, A Resolution to Approve the Preliminary Design and Authorize Staff to Proceed with Final Design, Right-of-Way Acquisition and Construction Bidding Phase for the 100 Block Battle Avenue Drainage improvements project. 

 

On April 28, 2015, the Board of Mayor and Aldermen approved amendment no. 1 to the Professional Services Agreement (COF Contract 2013-0180) for additional engineering design services on the 100 Block Battle Avenue Drainage Improvements Project. 

 

On October 10, 2017, the Board of Mayor and Aldermen approved a Professional services Agreement (COF Contract No. 2017-0251) with R. Rhett Turner, MAI for Right-of-Way Acquisition Services for the Battle Avenue Stormwater Project.

 

Staff has always assumed that the majority of the property owners would be willing to dedicate the easements associated with the project.  Some of the property owners are not willing to dedicate the easements while others will not be allowed to dedicate easements based on leans associated with mortgages.  The estimated cost of the project has increased substantially and staff would like to present alternative options and solutions for the Board to consider and provide direction on how to proceed with the project.

 

Financial Impact

No Financial Impact at this time.

 

Recommendation

rec

Staff is seeking direction from the Board and supports proceeding with Option 1 and Option 2B as capital projects to be funded from the Stormwater Capital Budget.