File #: 18-0414    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 4/19/2018 In control: Work Session
On agenda: 5/8/2018 Final action: 5/8/2018
Title: *Consideration of Amendment No. 5 to the Professional Services Agreement (COF Contract No. 2013-0034) with CDM Smith, Inc. for the Mack Hatcher Extension Project [SR-397 Mack Hatcher Parkway West, from South of SR-96, West of Franklin, to East of SR-106 (US-431), North of Franklin, Williamson County] at a Cost Increase Not-to-Exceed $32,640.00
Sponsors: Engineering
Attachments: 1. COF 2013-0034 - Mack Hatcher Amendment No 5_with attachment.Law Approved

 

DATE:                                                               April 19, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineer/Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering                     

                                          

SUBJECT:                                          

title

*Consideration of Amendment No. 5 to the Professional Services Agreement (COF Contract No. 2013-0034) with CDM Smith, Inc. for the Mack Hatcher Extension Project [SR-397 Mack Hatcher Parkway West, from South of SR-96, West of Franklin, to East of SR-106 (US-431), North of Franklin, Williamson County] at a Cost Increase Not-to-Exceed $32,640.00

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 5 to the Professional Services Agreement (PSA) (COF Contract No. 2013-0034) with CDM Smith, Inc.

 

Background

A brief history of the PSA (COF Contract No. 2013-0034) with CDM Smith, Inc. is as follows:

 

                     April 23, 2013                                          COF Contract No. 2013-0034, at the request of TDOT,

which allowed for the redesign of the project to included traditional signalized intersections.

 

                     November 24, 2014                     Amendment No. 1, at the request of TDOT, which allowed for the

redesign of the project as a two (2) lane facility.

 

                     February 9, 2016                     Amendment No. 2, at the request of TDOT, allowed for right-of-way

(ROW) plans revisions.

 

                     April 11, 2017                                          Amendment No. 3, at the request of TDOT, allows for additional ROW

Plans revisions, revisions to the Erosion Prevention and Sediment Control Plan, and additional geotechnical work.

 

                     September 12, 2017                     Amendment No. 4, at the request of TDOT, allows for Plan revisions to

prepare for bidding

 

Amendment No. 5 provides additional work that is necessary to update the plans to allow for bidding and ROW revisions.  The full details of this additional work can be seen in Attachment A.

 

Financial Impact

The cost of Amendment No. 5 is $32,640.00.  TDOT will reimburse this additional cost as a part of the project.  City staff will work with TDOT to prepare a contract amendment that will allow for reimbursement of these costs.

 

Recommendation

rec

Staff recommends approval of Amendment No. 5 to the PSA (COF Contract No. 2013-0034) with CDM Smith, Inc. in an amount not-to-exceed $32,640.00.