File #: 18-0291    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/29/2018 In control: Work Session
On agenda: 4/24/2018 Final action: 4/24/2018
Title: *Consideration of Resolution 2018-20 to Award the FY 2019 On-Call Annual Contract for Pavement Preservation (COF Contract No. 2018-0036) to Jarrett Builders, Inc.
Sponsors: Engineering
Attachments: 1. 2018-20 RES_FY19_OnCallAnnual_PavementPreservation.Law Approved

DATE:                                                               April 16, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineer/Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering                     

                                          

SUBJECT:                                          

title

*Consideration of Resolution 2018-20 to Award the FY 2019 On-Call Annual Contract for Pavement Preservation (COF Contract No. 2018-0036) to Jarrett Builders, Inc.

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2018-20 to award the FY 2019 On-Call Annual Contract for Pavement Preservation (seal coating) (COF Contract No. 2018-0036) to Jarrett Builders, Inc.

 

Background

The On-Call Annual Contract for Pavement Preservation will be used to extend the service life of asphalt pavements by placing seal coat and repairing cracks.  The Streets Department has evaluated several seal coating products and has performed a test of the seal coating methodology in the Golden Meadow Subdivision.  Based on this research, the Streets Department wishes to move forward to provide for street maintenance at a significantly reduced cost for roadways that meet the criteria for such application.

 

The public bid opening for COF Contract No. 2018-0036 was held on March 28, 2018.  While two (2) contractors picked-up bid packages, only one (1), Jarrett Builders, Inc., submitted a bid on this project.  Despite the low interest in this advertisement, the pricing proposed by Jarrett Builders, Inc. is well within reason for this type of work.

 

It is important to note that the quantities listed in the project manual are not guaranteed work and are simply used to provide a bid price that is comparable to the expected annual use of the on-call contract.  Therefore, the bid price of $208,875.00, as submitted by Jarrett Builders, Inc., is simply used as a fair comparison point in the competitive bid process. 

 

Financial Impact

The Street Department has set aside $300,000 of the budgeted Street Aid monies to perform this work in FY 2018 ($275,000 remaining).  The Street Department has requested an additional $300,000 for the FY 2019 budget, subject to approval.

 

Recommendation

rec

Staff recommends approval of Resolution 2018-20 to award the FY 2019 On-Call Annual Contract for Pavement Preservation (COF Contract No. 2018-0036) to Jarrett Builders, Inc.