File #: 18-0155    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 2/12/2018 In control: Capital Investment Committee
On agenda: 2/22/2018 Final action: 2/22/2018
Title: Consideration of Amendment No. 3 to the Professional Services Agreement (COF Contract No. 2014-0209) with CT Consultants, Inc. (formerly EG&G, Inc.) for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE not-to-exceed $25,000.00.
Sponsors: Paul Holzen, Jonathan Marston, William Banks
Attachments: 1. 2014-0209_PSA_Amend3_CTC_FranklinRdImprov_with Exhibit A.Law Approved_1

DATE: February 22, 2018

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of Amendment No. 3 to the Professional Services Agreement (COF Contract No. 2014-0209) with CT Consultants, Inc. (formerly EG&G, Inc.) for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE not-to-exceed $25,000.00.
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 3 to the Professional Services Agreement (PSA) (COF Contract No. 2014-0209) with CT Consultants, Inc. for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost increase not-to-exceed $25,000.00.

Background
On July 1, 2005, the City entered into a PSA with EG&G, Inc. for the Design of the Franklin Corridor & Connector Streets Economic Development Project - Segment One. The original Segment One phase included the following projects: Third Avenue North, Fifth Avenue North, Columbia Avenue, and Hillsboro Road. On June 19, 2007, the BOMA approved Amendment No. 6 to EG&G's Segment One PSA for the preliminary design of Franklin Road, from the Harpeth River Bridge to Harpeth Industrial Court (approx. 3,200 L.F.), in the amount of $195,250.00. On September 9, 2008, the BOMA approved Amendment No. 9 to EG&G's Segment One PSA for the final design of Franklin Road in the amount of $420,000.00. The final construction plans and specifications were never completed due to the economic downturn of 2008 and were shelved until recently.

On September 8, 2009, the BOMA approved the fiscal years (FY) 2010-2014 Ca...