Title: Capital Project Status Report

DATE: October 20, 2017

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Mark Hilty, Assistant City Administrator for Public Works
Paul P. Holzen, Director of Engineering
Michelle Hatcher, Director of Water Management


SUBJECT:
title
Capital Project Status Report
body

Transportation Project Status

A. Mack Hatcher Parkway NW Extension
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - October 2017; ROW Start - December 2009; ROW Completion - December 2017; Construction Bid Date - February 2018
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update: On May 9, 2017, TDOT released its annual 3-year (FY 2018-2020) transportation program. The construction of Mack Hatcher Parkway, from Highway 96 West (SR-96) to Hillsboro Road (SR-106) is included in the list of projects. It is programmed to receive funding in FY 2018. City and TDOT staff working toward a February letting date.

B. Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - March 2015; ROW Start - March 2013; ROW Completion - May 2015; Bid Date - January 2016; Construction Start - April 18, 2016; Original Construction Completion - June 21, 2017 (430 calendar days); Current Construction Completion - November 22, 2017 (CO#1 Additional 154 Calendar Days; 584 Calendar Days based upon delays and utility conflicts)
*Denotes Estimated Date
Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction Bid - $11,995,005.13 ($1,750,000 Reimbursable through State and Federally Approved Funding; Includes AT&T and ATMOS Reimbursable items totaling $441,677.00); Current Construction - $12,049,584.48 (CO#1)
Status Update: There have been numerous utility conflicts throughout the project. Change Order No. 1 was approved for a 1...