File #: 17-0778    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 8/25/2017 In control: Board of Mayor & Aldermen
On agenda: 9/12/2017 Final action: 9/12/2017
Title: Consideration of Amendment No. 4 to TDOT Agreement No. 120296 (COF Contract No. 2013-0022) for the Hunters Bend Elementary Safe Routes to School Project (PIN 118151.00) (8/24/2017 CIC 3-0)
Sponsors: Engineering
Attachments: 1. COF 2013-0022_TDOT Amnd 4_HuntersBendSRTS_Law Approved.pdf

DATE: August 24, 2017

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering

SUBJECT:
title
Consideration of Amendment No. 4 to TDOT Agreement No. 120296 (COF Contract No. 2013-0022) for the Hunters Bend Elementary Safe Routes to School Project (PIN 118151.00) (8/24/2017 CIC 3-0)
body

Purpose
The purpose of this memoradum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 4 to Tennessee Department of Transportation (TDOT) Agreement No. 120296 (COF Contract No. 2013-0022) for the Hunters Bend Elementary Safe Routes to School (SRTS) Project (PIN 118151.00.)

Background
The purpose of the Hunters Bend Elementary SRTS Project is to construct improvements to two (2) pedestrian tunnels and the surrounding area near Hunters Bend Elementary School. These improvements generally consist of: sidewalk replacement, earthwork, retaining wall construction, lighting, emergency call box, tunnel surround repair, and ADA improvements.

The history of the Local Agency Project Agreement (LAPA) (TDOT Agreement No. 120296; COF Contract No. 2013-0022) is as follows:

* April 23, 2013 - Original Agreement
* April 28, 2015 - Amendment No. 1 - Time Extension
* April 26, 2016 - Amendment No. 2 - Time Extension
* April 11, 2017 - Amendment No. 3 - Time Extension

The construction history of this project is:

* December 12, 2016 - Construction bids received and opened
* February 14, 2017 - BOMA awards construction bid
* April 20, 2017 - Pre-Construction Meeting
* April 24, 2017 - Effective Date of Notice to Proceed with Work
* July 24, 2017 - Scheduled Completion Date

The original LAPA with TDOT contained an Exhibit A (e.g. funding breakdown) of:

There have been several factors that have contributed to the significant cost overruns for this project. Those factors include:

* Significant delay during the design process
* Scope Creep
o Extended Project Limit...