Title: Consideration of Resolution 2017-59 Awarding the Construction Contract (COF Contract No. 2017-0079) for the Harpeth River Bank Stabilization Project at the City of Franklin Water Reclamation Facility to Viking Products, Inc. in the Amount of $311,782.21 (07/27/17 CIC 3-0)
Sponsors: Engineering
Attachments: 1. Harpeth Bank Stabilization Bid recommendation letter, 2. Res 2017-59 Harpeth River Bank Stabilization.Law Approved.pdf

 

DATE:                                                               July 27, 2017

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineer/Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering

                                          Jeff Willoughby, Stormwater Coordinator                     

                                          

SUBJECT:                                          

title

Consideration of Resolution 2017-59 Awarding the Construction Contract (COF Contract No. 2017-0079) for the Harpeth River Bank Stabilization Project at the City of Franklin Water Reclamation Facility to Viking Products, Inc. in the Amount of $311,782.21 (07/27/17 CIC 3-0) 

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2017-59 to award the construction contract (COF Contract No. 2017-0079) for the Harpeth River Bank Stabilization Project at the City’s Water Reclamation Facility to Viking Products, Inc.

 

Background

The left descending bank of the Harpeth River, at the City’s Water Reclamation Facility, has experienced significant erosion.  The river bank must be stabilized to prevent further erosion and to protect critical infrastructure at the Water Reclamation Facility.

 

On August 15, 2015, the BOMA approved a professional services agreement (PSA) (COF Contract No. 2015-0186) with Civil and Environmental Consultants, Inc. (CEC) to design this bank stabilization project.  On July 11, 2017, the BOMA approved Amendment No. 1 to this PSA for inspection services related to the construction of this project.

 

On June 26, 2017, the Engineering Department received, opened, and read aloud the submitted construction bids for this project.  Three (3) bids were received, with two (2) of the bidders being considered responsive.  After review the submitted documents and tabulation of the bids, staff recommends award of COF Contract No. 2017-0079 to the low bidder, Viking Products, Inc. in the amount of $311,782.21.

 

Financial Impact

Funding for this project has been budgeted and is available in the fiscal year (FY) 2018 annual operating budget for the Stormwater Division of the Engineering Department.  The General Ledger (GL) code to be used for project expenses is 135-89410-43125.

 

Recommendation

rec