DATE: July 20, 2017
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul P. Holzen, Director of Engineering
Jimmy Wiseman, Assistant Director of Engineering
SUBJECT: itle
Consideration of an Agreement (COF Contract No. 2017-0084) with Dominion Senior Living of Franklin LLC for Reimbursement of Cost for Water Distribution Improvements at a Cost of $9,586.09 (07/27/17 CIC 4-0)
body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning COF Contract No. 2017-0084
Background
Dominion Senior Living of Franklin LLC previously submitted to the Franklin Municipal Planning Commission Watson Glen Subdivision, Site Plan, Section 2 (Somerby) Project #5766 for approval. The developer was required, as a condition of approval, to construct certain off-site water distribution improvements, which became a part of the Franklin water distribution system. The improvements are available for the use and benefit of the businesses/residents within the development and other present/future customers of the City of Franklin.
The developer incurred a cost of $171,396.00 in the construction of the water improvements. Of this cost, it has been determined that the additional cost of upsizing the water main, as required by the City, was $9,586.09. The Developer is therefore entitled, pursuant to Section 18-108 of the Franklin Municipal Code, to be reimbursed for the upsize portion of the costs of construction.
Financial Impact
$9,586.09 - paid out of the water access fund.
Recommendation
Staff recommends approval of COF Contract No. 2017-0084 with Dominion Senior Living of Franklin LLC in the amount of $9,586.09.