File #: 17-0697    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 7/31/2017 In control: Board of Mayor & Aldermen
On agenda: 8/8/2017 Final action: 8/8/2017
Title: Consideration of Amendment #3 to the Professional Services Agreement for the Goose Creek Sanitary Sewer Extension Project from West of I65 to East of I65 (COF Contract No. 2014-0177) with Hethcoat and Davis in the Amount of $12,800.00. (07/27/17 CIC 3-0)
Sponsors: Mark Hilty, Michelle Hatcher, Patricia McNeese
Attachments: 1. Request Add RPR Services 062717, 2. COF 2014-0177 Amnd 3 PSA Hethcoat and Davis_with Attachment A.Law Approved

 

DATE:                                                               July 27, 2017

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Mark Hilty, Assistant City Administrator for Public Works                     

                                          Michelle Hatcher, Director Water Management

                                          Patricia McNeese, Utilities Project Manager

                                          

SUBJECT:                                          

title

Consideration of Amendment #3 to the Professional Services Agreement for the Goose Creek Sanitary Sewer Extension Project from West of I65 to East of I65 (COF Contract No. 2014-0177) with Hethcoat and Davis in the Amount of $12,800.00.  (07/27/17 CIC 3-0)

 

body

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the Amendment #3 to the Professional Services Agreement for the Goose Creek Sanitary Sewer Extension Project from West of I65 to East of I65 (COF Contract No. 2014-0177) with Hethcoat and Davis in the Amount of $12,800.00.

 

Background

The contractor for the project has requested an increase in the contract time of 60 days.  This amendment is for the increase in the construction services with the engineering consultant as a result of this increase.

 

Financial Impact

Increase to original contract in the amount of $12,800.00

 

Recommendation

rec

Staff recommends approval of Amendment #3 to the Professional Services Agreement for the Goose Creek Sanitary Sewer Extension Project from West of I65 to East of I65 (COF Contract No. 2014-0177) with Hethcoat and Davis in the Amount of $12,800.00.