DATE: May 25, 2017
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer
SUBJECT:
title
Consideration of Amendment No. 2 to the Professional Services Agreement, COF Contract No. 2014-0209, with CT Consultants, Inc. (Formerly EG&G, Inc.) for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements (Streetscape) Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE not-to-exceed $65,590.00. (6/22/17 CIC 3-0)
body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 2 to the Professional Services Agreement, COF Contract No. 2014-0209, with CT Consultants, Inc. (Formerly EG&G, Inc.) for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements (Streetscape) Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE not-to-exceed $65,590.00.
Background
On July 1, 2005, the City entered into a Professional Services Agreement with EG&G, Inc. for the Design of the Franklin Corridor & Connector Streets Economic Development Project - Segment One. The original Segment One phase included the following projects: Third Avenue North, Fifth Avenue North, Columbia Avenue, and Hillsboro Road. On June 19, 2007, the Board approved Amendment #6 to EG&G's Segment One PSA for the preliminary design of Franklin Road, from the Harpeth River Bridge to Harpeth Industrial Court (Approx. 3,200 L.F.), in the amount of $195,250.00. On September 9, 2008, the Board approved Amendment #9 to EG&G's Segment One PSA for the final design of Franklin Road in the amount of $420,000.00. The final construction plans and specifications were never completed due to the economic downturn of 2008, and was shelved until recently.