Title: Water and Sewer Projects Status Report
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE: March 30, 2017

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Mark Hilty, ACA of Public Works

SUBJECT:
title
Water and Sewer Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status

A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - March 2017*;
Easement Acquisition - TBD; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: The engineering consultant and Water Management Department staff are meeting on Monday, February 20, 2017, to discuss the 90% design plans. The project will not be constructed until funding is available from the Water Management Department budget.

B. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015; Easement Acquisition Completion - July 2017*; Bid Date: September 2017*; Construction Start - October 2017*; Construction Completion - August 2018*
*Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The plans are 100% complete. There have been delays with obtaining appraisals for some of the easements. Staff is working to resolve this issue.

C. Curd Branch and Watson Branch Interceptor Sewer
Key Dates: Design Start - February 25, 2014; Design Completion - September 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - June 2016; Bid Date: September 2016; Construction Start -February 2017; Construction Completion - October 2017*
*Denotes Estimated Date
Cost: Design - $115,000.00; Easeme...