Title: Consideration of A Resolution 2017-03, Awarding the Construction Contract (COF Contract No. 2016-0083) to Cleary Construction, Inc., in the Amount of $2,339,780.00 for the Ladd Park Interceptor Sewer Improvements Project. (1/26/2016 CIC 4-0)
Sponsors: Paul Holzen
Attachments: 1. PMF_170110_Ltr_Franklin_Ladd Park_Bid Award, 2. Ladd Park_Bid Summary, 3. Ladd Park_Bid Tab, 4. Res 2017-03 Ladd Park Sewer ProjectLaw Approved

DATE: January 26, 2017

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, P.E., Director of Engineering
Mark Hilty, P.E., Director of Water Management
Patricia McNeese, P.E., Utilities Engineer II

SUBJECT:
title
Consideration of A Resolution 2017-03, Awarding the Construction Contract (COF Contract No. 2016-0083) to Cleary Construction, Inc., in the Amount of $2,339,780.00 for the Ladd Park Interceptor Sewer Improvements Project. (1/26/2016 CIC 4-0)

body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2017-03, Awarding the Construction Contract (COF Contract No. 2016-0083) to Cleary Construction, Inc. in the amount of $2,339,780.00 for the Ladd Park Interceptor Sewer Improvements Project.

Background
On December 13, 2016, the Engineering Department received and opened bids for the Ladd Park Interceptor Sewer Improvements Project. The low bidder was Norris Construction, with a bid of $1,490,799.05.

Qualifications were requested from the low bidder per Section 00 2113 of the contract documents. Norris Brothers did not respond to the request. Norris Brothers was also the low bidder for the Curd Branch and Watson Branch Interceptor Improvements Project, but the bid was rejected due to lack of adequate experience for a project of that magnitude. The Ladd Park Interceptor Sewer Improvements Project has 18-inch and 24-inch diameter sanitary sewer lines that are 30+ feet deep. If Norris Brothers did not have the experience necessary to install 24" diameter sanitary sewer at approximately 10 feet in depth for the Curd Branch and Watson Branch Interceptor Sewer Improvements Project, then they would not qualify for the Ladd Park Interceptor Sewer Improvements Project.

The next lowest bidder, Cleary Construction, with a total bid price of $2,339,780.00, was able, upon request, to provide a list of ten (10) projects of sim...