File #: 17-0001    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 12/15/2016 In control: Board of Mayor & Aldermen
On agenda: 1/10/2017 Final action: 1/10/2017
Title: Consideration of Change Order No. 3 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (12/15/2016 CIC 4-0)
Sponsors: Paul Holzen, Jonathan Marston, William Banks
Attachments: 1. COF2014-0037_3rd_Ave_Trail-CO#3_Exhibit_A

DATE: December 13, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering/City Engineer
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer

SUBJECT:
Consideration of Change Order No. 3 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (12/15/2016 CIC 4-0)
body
Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 3 to the construction contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00).

Background
The 3rd Avenue North Trail/Greenway (Bicentennial Park Phase I) construction contract was awarded by the BOMA to Jones Bros. Contractors, LLC on August 11, 2015, in the amount of $1,253,257.31. The original contract completion date was scheduled for May 17, 2016 (240 Calendar Days). Change Order No. 1 was approved by BOMA on June 14, 2016. Change Order No. 1 included small changes required to properly complete the project and a request for additional time to the construction contract (75 additional calendar days). Change Order No. 2 was approved by BOMA on September 13, 2016. Change Order No. 2 included small changes required to properly complete the project and a request for additional time to the construction contract (23 additional calendar days).

The proposed Change Order No. 3 details include the following:
1. Add 16 calendar days to the original contract time due to weather delays and additional items of work. New contract completion date is September 9, 2016 (354 total calendar days).
2. Add Item No. 502-04.01 Saw cutting concrete to the contract. Additional irrigation ha...

Click here for full text