File #: 16-1046    Version: 1 Name:
Type: Item Approved on Behalf of the Board Status: Passed
File created: 11/28/2016 In control: Board of Mayor & Aldermen
On agenda: 12/13/2016 Final action: 12/13/2016
Title: Consideration of Change Order No. 1 to the Annual On-Call Sanitary Sewer Cleaning and Inspection Contract (COF Contract No. 2014-0273) with First Response for a Time Extension Through June 30, 2017
Sponsors: Mark Hilty
Attachments: 1. 2014-0273 Executed Copy_On Call Annual Contract for Sanitary Sewer Cleaning and Inspection

 

DATE:                                                               December 13, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Mark Hilty, P.E., Director of Water Management

                     

SUBJECT:                                          

title

Consideration of Change Order No. 1 to the Annual On-Call Sanitary Sewer Cleaning and Inspection Contract (COF Contract No. 2014-0273) with First Response for a Time Extension Through June 30, 2017

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen

(BOMA) concerning Change Order No. 1 to the Annual On-Call Sanitary Sewer Cleaning and Inspection

Contract (COF Contract No. 2014-02473) with First Response for a time extension through June 30,

2017.

 

Background

The Water Management Department utilizes the annual contract to provide services for televising larger diameter sanitary sewers and heavy cleaning of existing sanitary sewers in which the City has limited capabilities of handling. 

 

On May 26, 2015, the BOMA approved Resolution 2015-18, which awarded the Annual On-Call Sanitary Sewer Cleaning and Inspection Contract (COF No. 2014-0273) to First Response.  Because this is an annual contract with funding supplied from the Sewer Operating Budget, this contract must be extended on a yearly basis.  Change Order No. 1 would extend the contract time until June 30, 2017, which is the end of the current fiscal year (FY) 2017.

 

Financial Impact

Funding for this contract comes from the Sewer Operating Fund.

 

Recommendation

rec

Staff recommends approval of Change Order No. 1 to COF Contract No. 2014-0273 with First Response for a time extension through June 30, 2017.