File #: 16-0745    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 8/26/2016 In control: Board of Mayor & Aldermen
On agenda: 9/13/2016 Final action:
Title: Consideration of Change Order No. 1 (FINAL) to the Contract with Jenco Construction, Inc. for the Construction of Century-Beasley Connector Project (COF Contract No. 2015-0042; Resolution 2015-45) for a DECREASE of $91,155.88 (8-25-2016 CIC 4-0)
Sponsors: Paul Holzen
Attachments: 1. Century - Beasley Final Change Order
Related files: 16-0706

 

DATE:                                                               August 25, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineering

                                          Jonathan Marston, Assistant Director of Engineering

                                          Ben Worley, ROW Agent/Project Manager                     

                                          

SUBJECT:                                          

title

Consideration of Change Order No. 1 (FINAL) to the Contract with Jenco Construction, Inc. for the Construction of Century-Beasley Connector Project (COF Contract No. 2015-0042; Resolution 2015-45) for a DECREASE of $91,155.88 (8-25-2016 CIC 4-0)

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 (FINAL) with Jenco Construction, Inc. for the construction of the Century-Beasley Connector (COF Contract No. 2015-0042) for a DECREASE in cost of $91,155.88.

 

Background

The construction contract for the Century-Beasley Connector was awarded by the BOMA to Jenco Construction, Inc. on August 11, 2015 in the amount of $399,250.97.  This project was substantially complete and opened to traffic in July 2016.  The project has reached final completion is ready for final closeout.

 

Financial Impact

This DECREASE of $91,155.88 represents a 22.8% cost savings from the previously approved contract ceiling of $399,250.97.

 

Recommendation

rec

Staff recommends approval of Change Order No. 1 (FINAL) with Jenco Construction, Inc. for a DECREASE of $91,155.88 to COF Contract No. 2015-0042.