Title: Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0209) with EG&G, a Division of CT Consultants, Inc., for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements (Streetscape) Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a Cost INCREASE Not to Exceed $3,700.00 (01/28/16 CIC 4-0)
Sponsors: Engineering
Attachments: 1. COF 2014-0209 Franklin Rd PSA CT Amendment 1 FINAL - LA.pdf

DATE: January 28, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0209) with EG&G, a Division of CT Consultants, Inc., for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements (Streetscape) Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a Cost INCREASE Not to Exceed $3,700.00 (01/28/16 CIC 4-0)
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 1 to the Professional Services Agreement (PSA) (COF Contract No. 2014-0209) with EG&G, a Division of CT Consultants, Inc., for the Preparation of Final Plans and Specifications for the Franklin Road Corridor Improvements Project (also known as the Franklin Corridor & Connector Streets Economic Development Project Segment One- Franklin Road).

Background
On July 1, 2005, the City entered into a Professional Services Agreement with EG&G, Inc. for the Design of the Franklin Corridor & Connector Streets Economic Development Project - Segment One. The original Segment One phase included the following projects: Third Avenue North, Fifth Avenue North, Columbia Avenue, and Hillsboro Road. On June 19, 2007, the Board approved Amendment #6 to EG&G's Segment One PSA for the preliminary design of Franklin Road, from the Harpeth River Bridge to Harpeth Industrial Court (Approx. 3,200 L.F.), in the amount of $195,250.00. On September 9, 2008, the Board approved Amendment #9 to EG&G's Segment One PSA for the final design of Franklin Road in the amount of $420,000.00. The final construction plans and specifications were never completed due to the economic downturn of 2008, and was shelved until recently.

On September 8, 2009, BOMA approved th...