DATE: December 23, 2015
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering/City Engineer
SUBJECT:
title
Summary of Carlisle Lane Typical Sections, Project Limits and Cost Estimates
body
Purpose
The purpose of this memorandum is to provide information to the Board of Mayor and Aldermen (BOMA) to consider off-site improvements.
Background
Cardel Village submitted a Development Plan and a Rezoning Request on June 29, 2016. At the initial pre-application meeting, city staff told the developer that we would not support the request without improvements to Carlisle Lane to correct the alignment and address all safety concerns. Currently, the City has no funding in place to make improvements to Carlisle Lane. For this reason staff has recommended denial of the Development Plan and the Rezoning Request until this roadway can be upgraded to meet City Standards.
It should be noted that the Developer has the option to build under its current Estate Residential Zoning. If the Developer builds under its current zoning staff would not require any offsite improvements as part of the development.
Financial Impact
At the November 10, 2015 Board of Mayor and Aldermen meeting, staff was asked to re-evaluate multiple typical sections, project limits, and cost estimates. This information can be found in Exhibit A.
Recommendation
rec
No recommendation at this time. Staff is providing additional information as requested by the Board of Mayor and Aldermen.