File #: 15-0864    Version: 1 Name: PSA with SSR for Sewer Line Relocation Design
Type: Contract/Agreement Status: Passed
File created: 9/12/2015 In control: Board of Mayor & Aldermen
On agenda: 10/13/2015 Final action: 10/13/2015
Title: Consideration of a Professional Services Agreement (COF Contract No. 2015-0293) with Smith Seckman Reid, Inc. (SSR) for the Sanitary Sewer Line Relocation Design on the Franklin Road Corridor Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, for a Lump Sum Fee of $24,500.00 (09/24/15 CIC 3-0)
Sponsors: Paul Holzen, Engineering
Attachments: 1. COF 2015-0293 PSA SSR Sewer Relocation FINAL.pdf

DATE: September 24, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
Consideration of a Professional Services Agreement (COF Contract No. 2015-0293) with Smith Seckman Reid, Inc. (SSR) for the Sanitary Sewer Line Relocation Design on the Franklin Road Corridor Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, for a Lump Sum Fee of $24,500.00 (09/24/15 CIC 3-0)
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a Professional Services Agreement (COF Contract No. 2015-0293) with Smith Seckman Reid, Inc. (SSR) for the Sanitary Sewer Line Relocation Design on the Franklin Road Corridor Improvements Project, which is also known as the Franklin Corridor & Connector Streets Economic Development Project Segment One- Franklin Road.

Background
On July 1, 2005, the City entered into a Professional Services Agreement with EG&G, Inc. for the Design of the Franklin Corridor & Connector Streets Economic Development Project - Segment One. The original Segment One phase included the following projects: Third Avenue North, Fifth Avenue North, Columbia Avenue, and Hillsboro Road. On June 19, 2007, the Board approved Amendment #6 to EG&G's Segment One PSA for the preliminary design of Franklin Road, from the Harpeth River Bridge to Harpeth Industrial Court (Approx. 3,200 L.F.), in the amount of $195,250.00. On September 9, 2008, the Board approved Amendment #9 to EG&G's Segment One PSA for the final design of Franklin Road in the amount of $420,000.00. The final construction plans and specifications were never completed due to the economic downturn of 2008, and was shelved until recently. On September 8, 2009, BOMA approved the FY 2010-2014 CIP Projects and Priority Ranking. Franklin R...

Click here for full text