SILVER GRACE PUD SUBDIVISION, SITE PLAN, SECTION 1
Maint agreement: Landscaping Phase A $73,000
Established: May 16, 2014
Previous Action: 5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Rephased landscaping, Phase A is now the old Phase A, C and E, new original amount $291,000; Release PA, establish MA for $73,000.
6/10/14 MA posted
5/28/15 Extend to 5/26/16
Recommendation: Extend to May 25, 2017.
Reason/Deficiency: The dead Dogwood tree and the two dead Willow Oak trees shall be replaced.
Perf agreement: Landscaping Phase B $58,000
Established: August 26, 2010
Previous Action: 5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Extend to 5/15/15 (landscaping rephased; this is Phase B and has not changed).
5/28/15 Approved extension to 5/26/16
Recommendation: Approved extension to May 25, 2017. This area is still under construction.
Perf agreement: Landscaping Phase C $35,000
Established: August 26, 2010
Previous Action: 5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Rephased landscaping, Phase C is now the old Phase D, new original amount $35,000; Extend to 5/15/15.
5/28/15 Approved extension to 5/26/16
Recommendation: Approved extension to May 25, 2017. This area is still under construction.