File #: 17-1057    Version: 1 Name:
Type: Planning Item Status: Passed
File created: 11/22/2017 In control: Franklin Municipal Planning Commission
On agenda: 12/14/2017 Final action: 12/14/2017
Title: Westhaven PUD Subdivision, site plan, section 25; accept the drainage improvements, release the performance agreement and establish a maintenance agreement for one year. (CONSENT AGENDA)

WESTHAVEN PUD SUBDIVISION, SITE PLAN, SECTION 25

Perf agreement:                     Drainage $8,250

Established:                     November 14, 2008

Previous Action:                     12/17/08 PA posted

11/13/09 Approved extension to 7/16/10

7/16/10 Reduce 75% from $33,000; extend to 7/15/11

7/15/11 Approved extension to 1/20/12

1/26/12 Approved extension to 7/26/12

7/26/12 Approved extension to 1/24/13

1/24/13 Approved extension to 7/25/13

7/25/13 Approved extension to 1/23/14

1/23/14 Approved extension to 7/24/14

7/24/14 Approved extension to 1/22/15

1/22/15 Approved extension to 7/23/15

7/23/15 Extend to 7/28/16

7/28/16 Approved extension to 1/26/17

1/26/17 Approved extension to 7/27/17

7/27/17 Approved extension to 1/25/18

Recommendation:                     Extend to December 20, 2018.

Reason/Deficiency:                     The smallest bioretention area does not contain six-inches of ponding, as the curb cut next to the inlet is causing the water to bypass the area.  The central bioretention area appears to be a landscape bed, instead of a bioretention area.  The largest bioretention area appears to be holding water, contains sediment, and the required plants are not living.