BRENTWOOD POINTE III PUD SUBDIVISION, SITE PLAN, LOT 8 (THE VIEW)
Maint agreement: Landscaping (Phase 2) $4,000
Established: June 25, 2015
Previous Action: 10/22/09 FMPC split into Phase 1 & Phase 2; this is Phase 2 (the unbuilt portion) in new amount of $13,000. Extend to 10/28/10.
10/28/10 Extend to 10/27/11; still under construction
10/27/11 Approved extension to 10/25/12
10/25/12 Approved extension to 10/24/13
10/24/13 Approved extension to 10/23/14; still under construction
10/24/14 Approved extension to 10/22/15
6/25/15 Release PA, establish MA for $4,000
7/2/15 MA posted
Recommendation: Release the maintenance agreement.