MEDCORE MEDICAL BUILDING SUBDIVISION, SITE PLAN, LOT 2 (HEALTHSOUTH REHAB CENTER)
Perf agreement: Drainage $143,000
Established: September 14, 2011
Previous Action: 4/18/13 PA posted
4/17/14 Approved extension to 4/17/15
4/17/15 Approved extension to 4/15/16
4/15/16 Extend to 4/21/17
Recommendation: Extend to November 16, 2017.
Reason/Deficiency: Positive drainage shall be provided, as the detention pond is holding water. The retention pond French drain that has failed shall be repaired/replaced. The pervious concrete may need cleaning. Drainage as-builts shall be submitted.