PRESERVE AT ECHO ESTATES PUD SUBDIVISION, SITE PLAN
Maint agreement: Landscaping section 1 street trees $7,000
Established: June 16, 2017
Previous Action: 9/25/14 PA posted
10/16/15 Approved extension to 10/21/16
10/21/16 Approved extension to 10/20/17
6/16/17 Split into 3 phases; this is section 1 street trees; new original amount $27,600; Release PA, establish MA for $7,000.
7/5/17 MA posted
Recommendation: Release the maintenance agreement.
Maint agreement: Landscaping section 2 street trees $8,000
Established: June 16, 2017
Previous Action: 9/25/14 PA posted
10/16/15 Approved extension to 10/21/16
10/21/16 Approved extension to 10/20/17
6/16/17 Split into phases; this is section 2 street trees; new original amount $30,600; Release PA, establish MA for $8,000.
7/5/17 MA posted
Recommendation: Extend to June 27, 2019.
Reason/Deficiency: The dead tree in front of lot 37 and the dead tree in front of open space lot 46 shall be replaced. The missing tree in front of lot 26 shall be installed.
Perf agreement: Landscaping section 1 buffers $63,400
Established: October 16, 2013
Previous Action: 6/16/17 Split into phases; this is section 1 buffers; new original amount $63,400; extend to 6/15/18.
Recommendation: Approved extension to June 27, 2019.
Perf agreement: Landscaping section 1 open space $56,000
Established: October 16, 2013
Previous Action: 6/16/17 Split into phases; this is section 1 open space; new original amount $56,000; extend to 6/15/18.
Recommendation: Approved extension to June 27, 2019.
Perf agreement: Landscaping section 2 buffers $23,100
Established: October 16, 2013
Previous Action: 6/16/17 Split into phases; this is section 2 buffers; new original amount $23,100; extend to 6/15/18.
Recommendation: Approved extension to June 27, 2019.
Perf agreement: Landscaping section 2 open space $74,300
Established: October 16, 2013
Previous Action: 6/16/17 Split into phases; this is section 2 open space; new original amou...