DATE: March 4, 2015
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering
SUBJECT:
title
Street Projects Status
body
Purpose
The purpose of this memo is to update the City of Franklin Board of Mayor and Aldermen (BOMA) with the current status of some of the City's street projects.
Project Status
A. Mack Hatcher Parkway NW Extension
BOMA Priority Ranking: N/A (Highest Priority)
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009 (ROW Meeting Scheduled); ROW Completion - June 2012; Construction Start - Currently Not Funded; Construction Completion - Currently Not Funded
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update: TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction. The designer is completing final plans comments, as requested by TDOT.
B. Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
BOMA Priority Ranking: #1
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - February 2015; ROW Start - March 2013; ROW Completion - March 2015*; Bid Date - May 2015*; Construction Start - July 2015*; Construction Completion -September 2016*
*Denotes Estimated Date
Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction - $12,500,000.00 ($1,750,000 Reimbursable through State and Federal Approved Funding)
Status Update: ROW Acquisition is still ongoing. All offers have been made. Waiting on closings and condemnation proceedings to start. Construction Plans are complete. Will hopefully have TDOT concurrence to bid the project in March/April.
C. Carothers Parkway South Exte...
Click here for full text