DATE: October 27, 2016
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
SUBJECT:
title
Stormwater Projects Status Report
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's stormwater projects.
Project Status
A. 100-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - August 2016*; Easement Acquisition Start - November 2016*; Easement Acquisition Completion - April 2017*; Bid Date - June 2017*; Construction Start - July 2017*; Construction Completion - October 2017*
*Denotes Estimated Dates
Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00
Status Update: The final design should be submitted to the City by the middle of October. ROW Acquisition could begin in Fall of 2016.
B. Figuers Drive and 400-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Construction Start - TBD; Construction Completion - TBD;
Cost: Initial Design - $82,000.00; Final Design - $125,200.00; Construction - TBD (engineering estimate)
Status Update: Water and sanitary sewer design contract amendments are approved by Law, and scheduled for a November BOMA agenda. During design, existing water line and sanitary sewer line conflicts were discovered. These will be relocated to accommodate the proposed drainage improvements.
C. Jordan Branch of Spencer Creek (Cool Springs East) Stream Restoration
Key Dates: Design Start - May 26, 2015 (BOMA Approved); Design Completion - December 2016*; ROW/Easement Acquisition - TBD; Construction - TBD
*Denotes E...
Click here for full text