File #: 16-0414    Version: 1 Name:
Type: Report Status: Passed
File created: 4/25/2016 In control: Capital Investment Committee
On agenda: 4/28/2016 Final action: 4/28/2016
Title: Water and Sewer Projects Status Report

DATE: April 25, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering


SUBJECT:
title
Water and Sewer Projects Status Report
body

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status

A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2016*;
Easement Acquisition - TBD; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Design plans are still being developed and are approximately 90% complete. The project will not be constructed until funding is available from the Water Management Department budget.

B. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015; Easement Acquisition Completion - August 2016*; Bid Date: October 2016*; Construction Start - December 2016*; Construction Completion - September 2017*
*Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The plans are 100% complete. Easement acquisition is still underway.



C. Curd Branch and Watson Branch Interceptor Sewer
Key Dates: Design Start - February 25, 2014; Design Completion - September 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - May 2016*; Bid Date: July 2016*; Construction Start -September 2016*; Construction Completion - August 2017*
*Denotes Estimated Date
Cost: Design - $115,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: Design pl...

Click here for full text