File #: 14-585    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/31/2014 In control: Board of Mayor & Aldermen
On agenda: 11/25/2014 Final action: 11/25/2014
Title: Consideration of Resolution No. 2014-76, A Resolution Rejecting all Bids for the Construction of the North Petway Sanitary Sewer Improvements Project (COF Contract No. 2014-0152) (11/12/14 CIC 3-0).
Sponsors: David Parker
Attachments: 1. RES 2014-76_NorthPetwaySS_RejectBids
 
DATE:                  October 31, 2014
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineer/CIP Executive
            Paul Holzen, Director of Engineering
            Mark Hilty, Director of Water Management
            Patricia Proctor, Utilities Engineer II
      
            
SUBJECT:            
title
Consideration of Resolution No. 2014-76, A Resolution Rejecting all Bids for the Construction of the North Petway Sanitary Sewer Improvements Project (COF Contract No. 2014-0152) (11/12/14 CIC 3-0).
body
 
Purpose
The purpose of this memo is to recommend that the Board of Mayor and Aldermen (BOMA) reject the bid submitted for the North Petway Sanitary Sewer Improvements Project (COF 2014-0152).
 
Background
This project has been identified by City of Franklin staff for rehabilitation due to the condition of the existing sanitary sewer lines.  The design for the project was approved by the Board of Mayor and Aldermen (BOMA) at the October 23, 2012 meeting.  The bids for the project were opened on August 6, 2014 at 9:00 am with only one contractor submitting a bid.
 
Financial Impact
A bid from Heit Kamp was submitted in the amount of $414,561.75.  This amount exceeds the original cost estimate and is not competitive with only one bid.
 
Recommendation
Staff recommends to reject the bid from Heit Kamp and make this project the first to be installed when the Annual Contract for Sewer Rehabilitation is bid out.