DATE: November 10, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer
Paul Holzen, Director of Engineering

SUBJECT:
title
Project Status Update for the SR 96 East Sidewalk Project - Pinkerton Park to Mack Hatcher Parkway
body

Purpose
The purpose of this memorandum is to provide the Board of Mayor and Aldermen (BOMA) with a status updated for the SR 96 East Sidewalk Project.

Background
As part of Resolution 2014-13, A Resolution to Adopt the Funding Plan for the FYI 2014-2018 CIP (Capital Investment Program) the Board approved $550,300 for a sidewalk project from Pinkerton Park to Mack Hatcher Parkway along HWY 96 E. On 2/19/2015 and 3/4/2015 a public hearing was held to obtain feedback from the local residents and the general public. The project was well supported by the residents with the majority of people in favor of the project. At the May 26, 2015 Board of Mayor and Alderman work session, city staff was directed to change the scope of work to incorporate a 10' wide multiuse trail along SR96E vs a 5' sidewalk. This change significantly increase the cost and scope of the project.

The project has been designed as an open ditch section to help reduce the construction cost and avoid relocation cost associated with overhead utilities. At this point the design is 95% complete and city staff continues to work with impacted utilities to include Atoms Gas, MTEMC, AT&T and Comcast. Utility Coordination should be completed in January. Below is an updated project schedule:

Task
Planned Start Date
Planned Finish Date
Public Meeting
December 2015
December 2015
ROW Acquisition
January 2016
May 2016
Bid Construction Project*
June 2016
June 2016
BOMA Award Contract*
July 2016
July 2016
Construction*
August 2016
November 2016
* This schedule is contingent upon staff being able to obtain 30 easement prior to June of 2016.


Financial Impact