RIZER POINT PUD SUBDIVISION, SITE PLAN, SECTION 1
Maint agreement: Sewer $37,700
Established: March 21, 2014
Previous Action: Six-month approval extension on 7/17/13 to 2/15/14
8/16/13 Reduce 75% from $377,000; extend to 8/15/14
8/21/13 PA posted
3/21/14 Release PA, establish MA for $37,700
4/3/14 MA posted
3/20/15 Extend to 9/18/15
9/18/15 Extend to 3/18/16
3/18/16 Extend to 9/16/16
9/22/16 Extend to 9/28/17
9/28/17 Extend to 3/27/18; applicant still working on a resolution to expose the manhole.
Recommendation: Release the maintenance agreement.
Perf agreement: Landscaping Phase 2 $53,000
Established: August 15, 2012
Previous Action: 5/15/15 Split into Phase 1 & 2; This is Phase 2, new original amount $53,000; extend to 5/20/16.
5/20/16 Extend to 5/19/17
5/25/17 Extend to 5/24/18
Recommendation: Extend to May 23, 2019. The applicant is currently working to certify the pond meets volume requirements and already has plans to complete the landscaping in this area when it is confirmed no more site work is required.
Perf agreement: Sidewalks $8,750
Established: August 15, 2012
Previous Action: Six-month approval extension on 7/17/13 to 2/15/14
8/21/13 PA posted
7/18/14 Reduce 75% from $35,000; extend to 7/17/15
7/17/15 Extend to 7/15/16
3/18/16 Release denied; extend to 3/17/17; 3 lots not complete
3/23/17 Extend to 3/22/18
3/22/18 Extend to 3/28/19
Recommendation: Extend to November 15, 2018.
Reason/Deficiency: All sidewalks must be complete.