File #: 18-1270    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 12/11/2018 In control: Work Session
On agenda: 1/8/2019 Final action: 1/8/2019
Title: *Consideration of Amendment No. 4 to the Professional Services Agreement (COF Contract No. 2014-0209) with CT Consultants, Inc. for the Preparation of Final Plans and Specifications for the Franklin Road Corridor (Streetscape) Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE Not-to-Exceed $103,740.00.
Sponsors: Paul Holzen
Attachments: 1. 18-1270 COF 2014-0209 - FRANKLIN ROAD AMENDMENT 4_with Exhibit.Law Approved.pdf, 2. DRAFT_COF2014-0209_Franklin_Road_StScape_CTC_PSA_Amend_4, 3. COF2014-0209_Franklin_Road_Amendment_4_Exhibit_A_Scope

DATE: January 8, 2019

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer

SUBJECT:
title
*Consideration of Amendment No. 4 to the Professional Services Agreement (COF Contract No. 2014-0209) with CT Consultants, Inc. for the Preparation of Final Plans and Specifications for the Franklin Road Corridor (Streetscape) Improvements Project, from the Harpeth River Bridge to Harpeth Industrial Court, at a cost INCREASE Not-to-Exceed $103,740.00.
body

Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 4 to the Professional Services Agreement (PSA) with CT Consultants, Inc. for the preparation of final plans and specifications for the Franklin Road Corridor (Streetscape) Improvements Project.

Background
On July 1, 2005, the City entered into a PSA with EG&G, Inc. for the Design of the Franklin Corridor & Connector Streets Economic Development Project - Segment One. The original Segment One phase included the following projects: Third Avenue North, Fifth Avenue North, Columbia Avenue, and Hillsboro Road. On June 19, 2007, the BOMA approved Amendment #6 to EG&G's Segment One PSA for the preliminary design of Franklin Road, from the Harpeth River Bridge to Harpeth Industrial Court (Approx. 3,200 L.F.), in the amount of $195,250.00. On September 9, 2008, the BOMA approved Amendment #9 to EG&G's Segment One PSA for the final design of Franklin Road in the amount of $420,000. Due to the economic downturn of 2008, the final construction plans and specifications were never completed and were shelved until recently.

On September 8, 2009, the BOMA approved the FY 2010-2014 CIP Projects and Priority Ranking. Franklin Road had a Priority Ranking of 8 but was not funded for right-of-way acquisition or construction. O...

Click here for full text