SOUTH PARK SUBDIVISION, SITE PLAN, SECTION 1, REVISION 2, LOT 7 (KEYSTONE CENTER)
Perf agreement: Access $5,000
Established: October 27, 2005
Previous Action: 1/13/06 PA posted
1/12/07 Extend to 10/25/07
10/25/07 Reduce from $10,000; extend to 10/23/08
10/17/08 Approved extension to 4/17/09
4/17/09 Approved extension to 4/16/10
NEW APPLICANT 10/1/09
4/22/10 Extend to 4/28/11
4/28/11 Approved extension to 4/26/12
4/26/12 Extend to 4/25/13
4/25/13 Extend to 4/24/14
4/24/14 Extend to 10/23/14
10/23/14 Extend to 10/22/15
10/22/15 Approved extension to 10/27/16
Recommendation: Approved extension to October 26, 2017. Construction has not begun on Building B.
Perf agreement: Sidewalks $3,000
Established: October 27, 2005
Previous Action: 1/13/06 PA posted
1/12/07 Extend to 10/25/07
10/25/07 Reduce from $6,000; extend to 10/23/08
10/17/08 Approved extension to 4/17/09
4/17/09 Approved extension to 4/16/10
NEW APPLICANT 10/1/09
4/22/10 Extend to 4/28/11
4/28/11 Approved extension to 4/26/12
4/26/12 Extend to 4/25/13
4/25/13 Extend to 4/24/14
4/24/14 Extend to 10/23/14
10/23/14 Approved extension to 10/22/15
10/22/15 Approved extension to 10/27/16
Recommendation: Approved extension to October 26, 2017. Construction has not begun on Building B.