RIZER POINT PUD SUBDIVISION, SITE PLAN, SECTION 1
Maint agreement: Sewer $37,700
Established: March 21, 2014
Previous Action: Six month site plan approval extension on 7/17/13 to 2/15/14
8/16/13 Reduce 75% from $377,000; extend to 8/15/14
8/21/13 PA posted
3/21/14 Release PA, establish MA for $37,700
4/3/14 MA posted
3/20/15 Extend to 9/18/15
9/18/15 Extend to 3/18/16
3/18/16 Extend to 9/16/16
Recommendation: Extend to September 28, 2017.
Reason/Deficiency: Expose the manhole covered in concrete. The applicant reports being aware of this issue and working towards a resolution.